|
United States
|
Office of Water
|
EPA 832-F-99-048
|
|
Environmental Protection
|
Washington
,
D.C.
|
September 1999
|
|
Agency
|
|
|

Storm Water Technology Fact Sheet
Wet Detention Ponds
DESCRIPTION
Wet detention ponds are
storm water control structures providing both retention and treatment of
contaminated storm water runoff. A
typical wet detention pond design is shown in Figure 1. The pond consists of a permanent pool of
water into which storm water runoff is directed.
Runoff from each rain event is detained and treated in the pond until it
is displaced by runoff from the next storm.
By capturing and retaining
runoff during storm events, wet detention ponds control both storm water
quantity and quality. The pond’s natural
physical, biological, and chemical processes then work to remove pollutants.
Sedimentation processes remove particulates, organic matter, and metals, while
dissolved metals and nutrients are removed through biological uptake. In
general, a higher level of nutrient removal and better storm water quantity
control can be achieved in wet
FIGURE 1 TYPICAL LAYOUT OF A WET DETENTION POND
detention ponds than can be achieved
with other Best Management Practices (BMPs), such as dry ponds,
infiltration trenches, or sand filters.
There are several common
modifications that can be made to the ponds to increase their pollutant removal
effectiveness. The first is to increase the settling area for sediments through
the addition of a sediment forebay, as shown in Figure 1. Heavier sediments will drop out of
suspension as runoff passes through the sediment forebay, while lighter
sediments will settle out as the runoff is retained in the permanent pool. A
second common modification is the construction of shallow ledges along the edge
of the permanent pool. These shallow
peripheral ledges can be used to establish aquatic plants that can impede flow
and trap pollutants as they enter the pond.
The plants also increase biological uptake of nutrients. In addition to their function as aquatic
plant habitat, the ledges also have several other functions, which can include
including acting as a safety precaution to prevent accidental drowning and
providing easy access to the permanent pool to aid in maintenance. Finally, perimeter wetland areas can also
be created around the pond to aid in pollutant removal.
APPLICABILITY
Wet detention ponds have
been widely used throughout the
U.S.
for many years. Many of these ponds have
been monitored to determine their performance. EPA Region V is currently
performing a study on the effectiveness of 50 to 60 wet detention ponds. Other
organizations, such as the
Washington
,
D.C.
, Council of Governments (WMCOG) and the Maryland Department of the Environment,
have also conducted extensive evaluations of wet detention pond performance.
ADVANTAGES AND
DISADVANTAGES
Wet detention ponds
provide both storm water quantity and quality benefits, and provide significant
retrofit coverage for existing development.
Benefits include decreased potential for downstream flooding and stream
bank erosion and improved water quality due to the removal of suspended solids,
metals, and dissolved nutrients.
While the positive impacts
from a wet detention ponds will generally exceed any negative impacts,
wet detention ponds that are improperly
designed, sited, or maintained, may have potential adverse affects on water
quality, groundwater, cold water fisheries, or wetlands.
Improperly designed or maintained ponds
may result in stratification and anoxic conditions that can promote the
resuspension of solids and the release of nutrients and metals from the trapped
sediments. In addition, precautions should be taken to prevent damage to
wetland areas during pond construction.
Finally, the potential for groundwater contamination should be carefully
evaluated. However, studies to date
indicate that wet detention ponds do not significantly contribute to groundwater
contamination (Schueler, 1992).
The following limitation
should also be considered when determining the feasibility of installing a wet
detention pond:
1. Wet
detention ponds must be able to maintain a permanent pool of water. Therefore,
ponds cannot be constructed in areas where there is insufficient precipitation
to maintain the pool or in soils that are highly permeable. In wetter regions, a small drainage area
may be sufficient to ensure that there is enough water to maintain a permanent
pool; whereas in more arid regions, a larger drainage area may be required. In
some cases, soils that are highly permeable may be compacted or overlaid with
clay blankets to make the bottom less permeable.
2. Land constraints, such as small sites or highly developed areas, may preclude the
installation of a pond.
3. Discharges from ponds usually consist of warm water, and thus pond use may be limited in areas
where warm water discharges from the pond will adversely impact a cold water
fishery.
4. The local climate (i.e., temperature) may affect the biological uptake in the pond.
5.
Without proper maintenance, the
performance of the pond will drop off sharply. Regular cleaning of the forebays
is particularly important.
Maintaining the permanent pool is also
important in preventing the resuspension of trapped sediments. The accumulation
of sediments in the pond will reduce the pond’s storage capacity and cause a
decline in its performance. Therefore, the bottom sediments in the permanent
pool should be removed about every 2 to 5 years. In most cases, no specific limitations
have been placed on disposal of sediments removed from wet detention ponds.
Studies to date indicate that pond
sediments are likely to meet toxicity limits and can be safely landfilled
(NVPDC, 1992). Some states have
allowed sediment disposal on-site, as long as the sediments are deposited away
from the shoreline to prevent their re-entry into the pond.
DESIGN CRITERIA
In general, pond designs
are unique for each site and application. Criteria for selecting the site for
installation of the pond should include the site’s ability to support the pond
environment, as well as the cost effectiveness of locating a pond at that
specific site. In addition, the pond
should be located where the topography of the site allows for maximum storage at
minimum construction costs (NVPDC, 1992).
Site-specific constraints for pond construction may include wetlands impacts,
existing utilities (e.g., electric or gas) that would be costly to relocate, and
underlying bedrock that would require expensive blasting operations to excavate.
The site must have
adequate base-flow from the groundwater or from the drainage area to maintain
the permanent pool. Typically, underlying soils with permeabilities of between
10-5 and
10-6 cm/sec will be adequate to maintain a
permanent pool.
All local, state and
federal permit requirements should be established prior to initiating the pond
design. Depending on the location of the pond, required permits and
certifications may include wetland permits, water quality certifications, dam
safety permits, sediment and erosion control plans, waterway permits, local
grading permits, land use approvals, etc.(Schueler, 1992). Since many states and municipalities are
still in the process of developing or modifying storm water permit requirements,
the applicable requirements should be confirmed with the appropriate regulatory
authorities.
Wet detention ponds should
be designed to meet both storm water quality and quantity control requirements.
Storm water quantity requirements are typically met by designing the pond to
control post-development peak discharge rates to pre-development levels. Usually the pond is designed to control
multiple design storms (e.g. 2-and/or 10-year storms) and safely pass the
100-year storm event. However, the design
storm may vary depending on local conditions and requirements.
Storm water quality control is achieved
through pollutant removal in the permanent pool.
Removal efficiency is primarily
dependent on the length of time that runoff remains in the pond, which is known
as the pond’s Hydraulic Residence Time (HRT). As discussed above, wet
detention ponds remove pollutants through both sedimentation and biological
uptake processes, both of which increase with the length of time runoff remains
in the pond. These processes can be modeled to determine a design HRT using
either the solids settling method or the eutrophication method, respectively
(Hartigan, 1988).
The calculated HRT will be
dependent on the method selected. HRTs calculated by the eutrophication method
can be up to three times greater than HRTs calculated by the solids settling
method. The longer HRTs associated with the eutrophication method appear to be
due to the slower reaction rates associated with the biological removal of
dissolved nutrients (Hartigan, 1988).
Once the design HRT has been determined,
the actual dimensions of the pond must be calculated to achieve the design HRT.
The primary factor contributing to a
pond’s HRT is its volume. Because many wet detention ponds are restricted in
area, pond depth can be an important factor in the pond’s overall volume.
However, the depth of the pool also
affects many of the pond’s removal processes, and so it must be carefully
controlled.
It is important to maintain a
sufficient permanent pool depth in order to prevent the resuspension of trapped
sediments (NVPDC, 1992).
Conversely, thermal stratification and anoxic conditions in the bottom layer
might develop if permanent pool depths are too great. Stratification and anoxic conditions may
decrease biological activity. Anoxic conditions may also increase the potential
for the release of phosphorus and heavy metals from the pond sediments (NVPDC,
1992). These factors dictate that the permanent pool depth should not exceed 6
meters (20 feet). The optimal depth
ranges between 1 and 3 meters (3 and 9 feet) for most regions, given a 2 week
HRT (Hartigan, 1988).
Other key factors to be
considered in the pond design are the volume and area ratios. The volume ratio, VB/VR, is the ratio of
the permanent pool storage (VB) to the mean storm runoff (VR). Larger VBs and
smaller VRs provide for increased retention and treatment between storm events. Low VB/VR ratios result in poor pollutant
removal efficiencies.
The area ratio, A/As, is
the ratio of the contributing drainage area (A) to the permanent pool surface
area (As). The area ratio is also an
indicator of pollutant removal efficiency.
Data from previous studies indicates that area ratios of less than 100
typically have better pollutant removal efficiencies (MD DEQ, 1986).
The contours of the pond are also
important.
The pond should be constructed
with adequate slopes and lengths.
While a length-to-width ratio is usually not used in the design of wet detention
ponds for storm water quantity management, a 2:1 length-to-width ratio is
commonly used when water quality is of concern. In general, high length-to-width
ratios (greater than 2:1) will decrease the possibility of short-circuiting and
will enhance sedimentation within the permanent pool.
Baffles or islands can also be added
within the permanent pool to increase the flow path (Hartigan, 1988). Shoreline
slopes between 5:1 and 10:1 are common and allow easy access for maintenance,
such as mowing and sediment removal (Hartigan, 1988). In addition, wetland
vegetation is difficult to establish and maintain on slopes steeper than 10:1.
Ponds should be wedge-shaped so that flow enters the pond and gradually spreads
out. This minimizes the potential for
zones with little or no flow (Urbonas, 1993).
The design of the wet pond
embankment is another key factor to be considered. Proper design and construction of the
embankments will prolong the integrity of the pond structure. Subsidence and settling will likely occur
after an embankment is constructed. Therefore during construction, the
embankment should be overfilled by at least 5 percent (SEWRPC, 1991). Seepage through the embankment can also
affect the stability of the structure. Seepage can generally be minimized by
adding drains, anti-seepage collars, and core trenches.
The embankment side slopes can be protected from erosion by using minimum side
slopes of 2:1 and by covering the embankment with vegetation or rip-rap.
The embankment should also have a
minimum top width of 2 meters (6 feet) to aid in maintenance.
Finally, the internal flow
control of the pond must be considered. Discharge from the pond is controlled by
a riser and an inverted release pipe. Normal flows will be discharged through
the wet pond outlet, which consists of a concrete or corrugated metal riser and
barrel. The riser is a vertical pipe or
inlet structure that is attached to the base with a watertight connection. Risers are typically placed in or adjacent
to the embankment rather than in the middle of the pond. This provides easy access for maintenance
and prevents the use of the riser as a recreation spot (e.g. diving platform for
kids) (Schueler, 1988). The barrel is a horizontal pipe attached to the riser
that conveys flow under the embankment.
Typically, flow passes
through an inverted pipe attached to the riser, as shown in Figure 1, while
higher flows will pass through a trash rack installed on the riser. The inverted pipe should discharge water
from below the pond water surface to prevent floatables from clogging the pipe
and to avoid discharging the warmer surface water. Clogging of the pipe could result in
overtopping of the embankment and damage to the embankment (NVPDC, 1992). Flow is conveyed through the near
horizontal barrel and is discharged to the receiving stream. Rip-rap, plunge pools, or other energy
dissipators, should be placed at the outlet to prevent scouring and to minimize
erosion. Rip-rap also provides a
secondary benefit of re-aeration of the pond discharges.
Planners should consider
both the design storm and potential construction materials when designing and
constructing the riser and barrel.
Generally, the riser and barrel are sized to meet the storm water management
design criteria (e.g. to pass a 2-year or a 10-year storm event). In many installations, the riser and
barrel are designed to convey multiple design storms (Urbonas, 1993). To increase the life of the outlet, the riser and barrel should be constructed
of reinforced concrete rather than corrugated metal pipe (Schueler, 1992). The riser, barrel, and base should also
provide have sufficient weight to prevent flotation (NVPDC, 1992).
In most cases, emergency
spillways should be included in the pond design.
Emergency spillways should be sized to safely pass flows that exceed the
design storm flows. The spillway prevents
pond water levels from overtopping the embankment, which could cause structural
damage to the embankment. The emergency
spillway should be located so that downstream buildings and structures will not
be negatively impacted by spillway discharges. The pond design should include a
low flow drain, as shown in Figure 1. The
drain pipe should be designed for gravity discharge and should be equipped with
an adjustable gate valve.
PERFORMANCE
The primary pollutant removal mechanism
in a wet detention pond is sedimentation.
Significant loads of suspended
pollutants, such as metals, nutrients, sediments, and organics, can be removed
by sedimentation. Other pollutant removal mechanisms include algal uptake,
wetland plant uptake, and bacterial decomposition (Schueler, 1992).
Dissolved pollutant removal also occurs as a result of biological and chemical
processes (NVPDC, 1992).
The removal rates of
conventional wet detention ponds (i.e., without the sediment forebay or
peripheral ledges) are well documented and are shown in Table 1. The wide range in the removal rates is a
result of varying hydraulic residence times (HRTs), which is further discussed
in the Design Criteria section. Increased
pollutant removal by biological uptake and sedimentation is correlated with
increased HRTs. Proper design and maintenance also effect pond performance.
Studies have shown that
more than 90 percent of the pollutant removal occurs during the quiescent period
(the period between the rainfall events) (MD DEQ, 1986). However, some removal occurs during the
dynamic period (when the runoff enters the pond).
Modeling results have indicated that two-thirds of the sediment,
nutrients and trace metal loads are removed by sedimentation within 24
TABLE
1 REMOVAL EFFICIENCIES FROM WET DETENTION PONDS
Parameter Percent
Removal
Schueler, Hartigan,
1992 1988
Total 50-90 80-90 Suspended Solid
Total 30-90 Phosphorus
Soluble 40-80 50-70 Nutrients
Lead 70-80
Zinc 40-50
Biochemical 20-40 Oxygen Demand or Chemical Oxygen Demand
1 hydraulic residence
time varies
2 hydraulic residence time of 2 weeks
Source: Schueler, 1992 & MD DEQ, 1986.
hours. These projections are supported by the
results of the EPA's 1993 National Urban Runoff Program (NURP) studies. However, other studies indicate that an
HRT of two weeks is required to achieve significant phosphorus removal (MD DEQ,
1986).
The pond’s treatment
efficiency can be enhanced by extending the detention time in the permanent pool
to up to 40 hours. This allows for a more
gradual release of collected runoff, resulting in both increased pollutant
removal and control of peak flows (Hartigan, 1988).
OPERATION AND
MAINTENANCE
Wet detention ponds
function more effectively when they are regularly inspected and maintained.
Routine maintenance of the pond includes mowing of the embankment and buffer
areas and inspection for erosion and nuisance problems (e.g. burrowing animals,
weeds, odors) (SEWRPC, 1991). Trash and
debris should be removed routinely to maintain an attractive appearance and to
prevent the outlet from becoming clogged.
In general, wet detention ponds should be inspected after every storm event. The
embankment and emergency spillway should also be routinely inspected for
structural integrity, especially after major storm events. Embankment failure could result in severe
downstream flooding. When any problems are observed during routine inspections,
necessary repairs should be made immediately.
Failure to correct minor problems
may lead to larger and more expensive repairs or even to pond failure.
Typically, maintenance includes repairs to the embankment, emergency spillway,
inlet, and outlet; removal of sediment; and control of algal growth, insects,
and odors (SEWRPC, 1991).
Large vegetation or trees that may
weaken the embankment should be removed. Periodic maintenance may also
include the stabilization of the outfall area (e.g. adding rip-rap) to prevent
erosive damage to the embankment and the stream bank. In most cases, sediments removed from wet
detention ponds are suitable for landfill disposal. However, where available,
on-site use of removed sediments for soil amendment will reduce maintenance
costs.
COSTS
Typical costs for wet
detention ponds range from $17.50-$35.00 per cubic meter ($0.50-$1.00 per cubic
foot) of storage area (CWP, 1998). The
total cost for a pond includes permitting, design and construction, and
maintenance costs. Permitting costs may
vary depending on state and local regulations. Typically, wet detention ponds
are less costly to construct in undeveloped areas than to retrofit into
developed areas. This is due to the cost
of land and the difficulty in finding suitable sites in developed areas. The cost of relocating pre-existing
utilities or structures is also a major concern in developed areas. Several studies have shown the
construction cost of retrofitting a wet detention pond into a developed area may
be 5 to 10 times the cost of constructing the same size pond in an undeveloped
area. Annual maintenance costs can
generally be estimated at 3 to 5 percent of the construction costs (Schueler,
1992). Maintenance costs include the
costs for regular inspections of the pond embankments, grass mowing, nuisance
control, debris and liter removal, inlet and outlet maintenance and inspection,
and sediment removal and disposal. Sediment removal cost can be decreased by as
much as 50 percent if an on-site disposal areas are available (SEWRPC, 1991).
REFERENCES
1.
1. Center for Watershed Protection, 1998. Cost and Benefits of Storm Water
BMPs.
2.
2. Hartigan, J.P., 1988 “Basis for Design of
Wet
Detention
Basin
BMPs,” in Design of Urban Runoff Quality Control. American Society of
Engineers. 1988.
3.
3. Maryland Department of the Environment, 1986. Feasibility and Design of Wet
Ponds to Achieve Water Quality Control.
Sediment and Storm Water
Administration.
4. Northern Virginia Planning District
Commission, Engineers and Surveyors Institute, 1992.
Northern Virginia
BMP Handbook.
1.
5. Schueler, T.R., 1992. A Current Assessment of Urban Best
Management Practices. Metropolitan
Washington
Council of Governments.
2.
6. Southeastern
Wisconsin
Regional Planning Commission, 1991. Costs for Urban
Nonpoint
Source
Water Pollution Control Measures. Technical Report No. 31.
3.
7. Urbonas, Ben and Peter Stahre, 1993.
Storm Water Best
Management Practices and Detention for Water Quality, Drainage and CSO
Management. PTR
Prentice Hall,
Englewood
Cliffs,
New Jersey
.
ADDITIONAL INFORMATION
City of Charlotte
,
North Carolina
Steve Sands Storm Water
Services, Engineering and Property Management
600 East 4th Street
Charlotte
,
NC
28202
Illinois EPA Charles
Fellman Auxiliary Point Source Program, Permit Section, Division of Water
Pollution Control 1021 N. Grand Avenue East, P.O. Box 19276 Springfield, IL
62794
Minnehaha Creek Watershed
District Pete Cangialosi Gray Freshwater Center, Navarre 2500 Shadywood Road,
Suite 37 Excelsior, MN 55331
Polk County
,
Florida
Bob Kollinger Natural
Resources and Drainage Division
4177 Ben Durrance Road
Bartow
,
FL
33830
City of Reynoldsburg
,
Ohio
Larry Ward Storm Water
Utility
7806 East Main Street
Reynoldsburg
,
OH
43068
Southwest Florida Water Management District Betty Rushton
2379 Broad Street
Brooksville
,
FL
34609